Week 7 EOC:Scheduling Issues

What is he/she moving in to? Veer Tower Condos.
There will be a renovation of all the furniture and materials needed from the choosing of the client. Plumbing and electrical will take a 2 to 3 weeks, Flooring will take up to 3 days depending on material. Wall tile will take 4 days along with any paint. Cabinets and counter tops will take 2 week to install. Furniture will take 3 days and accessories will take 1 day. From the point they sign the contract the items will be purchased. This Condo will be designed and look the way you want it!
From contract to move in date how long will it take? If nothing goes wrong at the most 3 months but shooting for 2 months.